Category
              Construction (Commercial) » Adaptive Re-Use of an Historic Building
          Price
              $20,000,001 & OVER
          Year
              2012
          Builder/Company
              John Holland Pty Ltd
          Prize
              Winner
          Project
              Equinix SY3 Data Centre
          This contract called for the conversion of a 1960s Harry Seidler designed heritage listed government stores warehouse, into a state-of –the-art data centre.
The works, including design, local and overseas procurement of major equipment, construction and final commissioning was completed in just 10 months.
This was a most complex and difficult project.
 
 
       
     
 
 
 
 
 
 
   
   
   
   
  